| 09/2009 | Approval of the project and receiving the building permit |
| 09/2011 | Start of construction |
| 12/2012 | End of construction of the pressing shop, start of installation of technology |
| 02/2013 | Installation of the steam boiler and the turbine with the generator |
| 04/2013 | Start of operation of the pressing shop |
| 09/2013 | End of construction of the power plant |
| 11/2013 | Starting the trial run of the power plant |
| 04/2015 | Final approval of the power plant, permanent operation |
| 08/2016 | Restoration of the boiler of the power plant |